On an international payments rollout I worked on, the ERP teams had continued developing the group’s chosen core model.
The idea was to standardise payment processes. But the teams had moved ahead without establishing how far that model could accommodate the payment methods used by different subsidiaries. Its limitations only became apparent during the rollout.
Some payment methods could not be handled as expected. Revisiting the design would have meant redoing part of the work, with consequences for the schedule.
To meet the deadlines, local teams had to find ways of working around those constraints. Some payments remained outside the common solution.
The programme met its deadline.
Yet the model covered less than expected, and the consequences for subsidiaries were never properly considered and decided upon.
Solved for whom?
The ERP teams had a delivery schedule. Central Finance wanted consistent processes. Subsidiaries, meanwhile, still had to make payments, including when the common model did not accommodate local requirements.
Local teams are often best placed to find a way forward. They know their banks, the payment methods available and the constraints in their own countries.
In this case, they found ways to keep operating without disrupting the timetable. They had to work around the model’s limitations, with little say over the consequences.
Some payments still sat outside the common solution. Subsidiaries therefore had to continue dealing with exceptions to a model whose very purpose was to standardise practices.
From the programme’s perspective, the rollout could continue. For the local teams, part of the problem remained.
When adaptability hides the problem
What stays with me is that the local teams did exactly what was expected of them: they found ways to keep payments running.
The subsidiaries could carry on paying. The programme could move forward. But the difficulties that had forced those workarounds had not gone away.
It would be easy to conclude that the project should have been better prepared. That would be true, but it would miss something important.
International rollouts always bring surprises. Banking practices, formats and local constraints do not always fit neatly into a common model.
And sometimes keeping an exception is entirely reasonable. Changing an entire solution to meet one particular requirement may make little sense.
So I do not think the problem was the existence of local adaptations.
What troubles me is that they became the chosen response without a proper examination of their consequences.
Which payments would remain outside the solution? For how long? What would subsidiaries still have to manage separately? And what did that mean for the original aim of standardisation?
Those questions deserved an explicit decision.
What does it mean to finish a project?
I know how much a deadline can matter. A rollout draws on people’s time, commits budgets and often determines when other work can begin. Postponing delivery is not a trivial choice.
But it is also worth asking what made the deadline possible.
A compromise could have been perfectly reasonable if it had been made openly. Its consequences could then have been assessed, and a decision taken about which exceptions to retain and which to address later.
Looking back, what strikes me most is not that the core model had limitations. In an international rollout, there will always be local requirements that nobody fully anticipated.
What troubles me more is that meeting the deadline could be seen as a satisfactory result without a proper discussion of what subsidiaries would still have to handle themselves.
Since then, when a project is said to have delivered on its commitments, there is another question I want to ask:
What had to be left out to meet the deadline, and who is now expected to deal with it?